Past Projects
S/N | DESCRIPTION | LOCATION | CLIENT | STATUS |
1. | Complete overhauling of 2nos. Nitrogen Compressors and 1no. Cooling water pump | Utility Unit of Port Harcourt Refining company | PHRC | COMPLETED 2013 |
2. | Installation and commissioning of nine stages centrifugal pump | Boiler Feed Water pump unit | SAPELE POWER STATION | COMPLETED 2013 |
3. | Sectional Replacement on 24” Pipeline Sectional Replacement on 10” Pipeline |
RAPELE TO UPS (GRAMEN) UPS to UGHELLI WEST LINE |
SPDC | COMPLETED 2012 |
4. | Expansion of Escravous – Lagos gas pipeline system phase 1 ELP 1 30” Pipeline | Adeje (Under Anotech) | SPDC | COMPLETED 2012 |
5 | 8”, 10” CLAMPING | KOKORI & UGHEVWGHE LINE | SPDC | COMPLETED 2012 |
6 | Laying of 4” & 2” Pipelines for pressure testing | NORTH BANK YOKRI UNDER (BJ TECH) | SPDC | COMPLETED, 2011 |
7 | Painting of Evwreni 30,000BPD Flow Station | OML 30 Evwreni | NPDC | 2017 Completed |